On November 25, 2026, the Cabinet Committee on Economic Affairs, led by Prime Minister Narendra Modi, approved the development of a second container terminal at Kamarajar Port Limited in Tamil Nadu. The project, estimated at ₹4,288.26 crore including GST, aims to significantly boost the port's cargo handling capacity and enhance its role in India's maritime trade.
The new terminal will be developed through a Public Private Partnership (PPP) on a Design, Build, Finance, Operate and Transfer (DBFOT) basis. The selected concessionaire will be responsible for arranging the investment, construction, and operation of the terminal over a concession period of 40 years. This approach aligns with Kamarajar Port's existing landlord-port model, where operational and maintenance services are outsourced while private sector participation drives new terminal development.
Terminal Capacity and Technical Specifications
The second container terminal is designed to handle an annual capacity of 2.0 million Twenty-foot Equivalent Units (TEUs), the standard measure for containerized cargo. The expansion will be implemented in two phases: Phase I, costing ₹2,429.32 crore, will provide a capacity of 1.1 million TEUs, while Phase II, with an investment of ₹1,858.94 crore, will add 0.9 million TEUs. The terminal will span 900 metres with a design draft of 18 metres, enabling it to accommodate vessels up to 400 metres in length and carrying up to 24,346 TEUs.
Kamarajar Port Limited will undertake dredging to maintain the required depth, with an estimated cost of ₹450 crore. This dredging is critical to ensure that ultra-large container vessels can access the terminal safely and efficiently.
Project Timeline and Tender Process
The government issued the Request for Qualification-cum-Request for Proposal (RFQ-cum-RFP) on August 20, 2026, inviting bids from interested parties. The bid opening took place on November 11, 2026. Upon awarding the concession, Phase I construction is expected to be completed within 24 months, with commercial operations commencing in the 25th month. Phase II construction will follow from months 25 to 48, with full commercial operations starting in the 49th month.
This phased approach allows the port to gradually ramp up capacity and manage investment risks effectively. The 40-year concession period provides long-term certainty for the concessionaire to recoup investments and operate the terminal sustainably.
Kamarajar Port's Unique Position in India's Maritime Sector
Kamarajar Port is India's only corporatised major port, registered as a company rather than a traditional government department. This unique institutional status enables greater operational flexibility and private sector engagement. The port currently operates under a landlord-port model, where it owns the infrastructure but outsources terminal operations to private players.
The addition of a second container terminal is expected to strengthen Kamarajar Port's position as a key gateway for container traffic on the east coast of India. By expanding capacity and accommodating larger vessels, the port aims to attract more shipping lines and boost trade connectivity for Tamil Nadu and neighboring states.